Case Studies: The Blanka Tunnel Complex, Czech Republic


Figure 1: Blanka tunnel complex, Czech Republic
Blanka Tunnel Complex
Project Type: Greenfield
Contract duration: original date for completion of all works was set to 2011(5 years) but has been postponed to 2016.
Project Time Line
1993: Project conceived
1998: Project company SATRA awarded the contract to prepare studies and design for the tunnel complex
2003: Planning decisions and zoning permit issued
2006: Launch of tenders
Other important dates
November 2009: Announcement that opening of the tunnel postponed by 13 months to 2012
May 2012: City of Prague ceases payments to contractors
January 2014: Arbitration between the city of Prague and Metrostav begins
September 2014: Arbitration ends
Early 2015: Evidence of technical problems related to dampness and cabling system.
May 2007: Second tender for technology part signed with ČKD DIZ
June 2007: