Case Studies: The Blanka Tunnel Complex, Czech Republic
Figure 1: Blanka tunnel complex, Czech Republic | |
Blanka Tunnel Complex | |
---|---|
Project Type: | Greenfield |
Contract duration: | original date for completion of all works was set to 2011(5 years) but has been postponed to 2016. |
Project Time Line | |
1993: | Project conceived |
1998: | Project company SATRA awarded the contract to prepare studies and design for the tunnel complex |
2003: | Planning decisions and zoning permit issued |
2006: | Launch of tenders |
Other important dates | |
November 2009: | Announcement that opening of the tunnel postponed by 13 months to 2012 |
May 2012: | City of Prague ceases payments to contractors |
January 2014: | Arbitration between the city of Prague and Metrostav begins |
September 2014: | Arbitration ends |
Early 2015: | Evidence of technical problems related to dampness and cabling system. |
May 2007: | Second tender for technology part signed with ČKD DIZ |
June 2007:
|